BAE, Army Research Lab Develop Tech to Automate Heavy Weld Operations for Combat Vehicles

  • Our Bureau
  • 10:14 AM, December 11, 2019
  • 3591
BAE, Army Research Lab Develop Tech to Automate Heavy Weld Operations for Combat Vehicles

BAE Systems and Army Research Laboratory (ARL) developed a robotic manufacturing cell to automate heavy weld operations for combat vehicles. 

Presently, the combat vehicle hulls are typically fabricated from thick armor plates that are manually welded together. Numerous weld passes are required at each weld seam, so it can take several days to weld together a base vehicle hull. While advanced welding technologies to reduce the number of weld passes have been tested and proven, many are deemed too hazardous to be performed by hand. 

"To improve the quality of combat vehicle weldments and reduce fabrication time, the U.S. Army Combat Capabilities Development Command Manufacturing Technology program funded the project," ARL said in a statement Tuesday.

"The development, integration, and prove-out of this robotic weld cell was achieved in partnership with BAE Systems in support of the Armored Multi-Purpose Vehicle program, which is the robotic weld cell's first Army customer," the statement read.

The new cell is equipped with an advanced welding technology called High Energy Buried Arc Welding, which enables high-quality, thick-plate welds with minimal passes. The cell also contains a high-capacity, multi-axis positioning system that can manipulate multi-ton vehicle structures into ideal welding positions.

The robotic weld cell has multiple benefits for next generation combat vehicles: the quality and performance of weldments is higher, which results in better vehicle protection; and the automation reduces welding time by nearly 80 percent, which will help the Army meet its critical delivery requirements. 

"The system is operational and currently being controlled manually," said Megan Lynch, ManTech project officer. "We are still in the learning and debugging phase. Getting to full operational capability will be a process, but we are on track to get there by FY21.

"Initially, the robot was operated with a thicker weld wire than what is currently being used, but technical difficulties required us to take a step back and go to a thinner wire. We are now ready to start looking into a thicker wire again," Lynch said. 

Using a thicker weld wire enables a higher weld deposition rate and fewer passes. This will reduce welding time and potentially increase weld performance, two goals of the project. Initial testing, however, showed the targeted weld wire size was too thick to feed and cool properly in the cell's existing design. The weld wire optimization study planned for FY20 will focus on how to resolve these issues.

Once transitioned, the robotic weld cell is expected to perform approximately 70 percent of the heavy welds for the AMPV hull and reduce vehicle weld time up to 80 percent. These changes will help the AMPV program and the Army meet their fielding goals.